Monrovia Renewal Banner
Print
Press Enter to show all options, press Tab go to next option

Monrovia Renewal is the largest public works project in the City's history!

This exciting initiative is making citywide repairs to our water and sewer pipelines, water facilities, streets, sidewalks, curbs and gutters. These improvements are expected to take 4-5 years to complete and cost $51.7 million.

Keep up to date on the project, related field work, and construction starting Summer 2016 through 2020.

Receive periodic project updates by subscribing to our email list:

Monrovia Renewal Construction

Updated on 05/30/2017 2:38 PM

Pictures of construction activities throughout town.

Monrovia Renewal South Area Work - Week of February 11, 2019

This week, Sequel Contractors will be working on utility asphalt patching and asphalt repairs throughout various locations in the project area.  The following week, depending on weather, Sequel will complete work on streets receiving a full reconstruct by placing the second (and final) layer of asphalt.  View the project area map below to see what roadwork improvements are coming to your neighborhood! 

South Area Street Improvements Overview Rev. 12-20-18


Monrovia Renewal is Coming to the North Section!

This week, the City's contractor, Sully-Miller Contracting Company, will begin mobilizing, performing inspection work for sewer repairs, and preliminary cleaning for sewer pipe improvements throughout various locations in the project area.  Please note that prior to work, Sully-Miller will be posting 'No-Parking' signs and circulating notices to residents in the affected areas.  Residents will receive additional notice forty-eight hours prior to work beginning.

The North Section includes all areas located north of, and including Hillcrest Boulevard, Grand Avenue, and Greystone Avenue.  The overall North Section improvements of Monrovia Renewal are significant, and includes the following scope of work:

  • Roadway improvements to over 2,300,000 square feet of roadway
  • Concrete replacement for sidewalk, curb and gutter repairs.
    • Approximately  9,000 square feet of sidewalk replacement
    • Approximately 27,000 linear feet of curb and gutter replacement
  • Sewer improvements and repairs
    • Removal and replacement of more than 5,250 linear feet of water pipeline
    • Removal and replacement of approximately 175 water service lines
  • Repairs and enhancements to the Oakglade Reservoir
    • Maintenance to the tank including concrete treatment and sealing to mitigate any potential leaks as well as additional site enhancements including improvements to the tanks pipelines, valves, roof, and overall site condition.

Prior to roadwork, all necessary water, sewer, and concrete work - curb, gutters, and driveway approaches - will be completed.  Below is a map indicating the roadwork for the North.  View the map to see what road work improvements are coming to your neighborhood!

North area map and legend

For more information on what work will be happening on your street and general inquiries about the Monrovia Renewal project, please contact the Public Works Division at (626) 932-5575 or email the Monrovia Renewal Project Team at monroviarenewal@ci.monrovia.ca.us.


Monrovia Renewal North Community Meeting

In case you missed it, the Presentation at the Monrovia Renewal North Community Meeting is now available for viewing.  At this meeting, City staff provided an overview of the construction activities, schedule, and impacts that will be taking place over the next several months in the North Area.

View the presentation here: Monrovia Renewal - North Community Meeting - 1.23.2019

If you need additional information, please contact the Public Works Division at (626) 932-5575.


Construction Notices

We will do our best to minimize the impacts on residents and business. Construction notices will be delivered to all residents and businesses in the impacted area(s) prior to work taking place. The notices will outline the work taking place, a schedule overview, and information on associated impacts, such as parking restrictions and driveway access:

  • Initial Notice – This notice will be distributed approximately one week prior to work commencing.
  • Two Day Notice – A final notice will be provided two days before the activity begins to serve as a reminder of the upcoming work and associated impacts.

In addition, parking notices will be posted in the areas where parking will be impacted. During these activities, there will be intermittent road closures and parking restrictions. Streets and driveways may be inaccessible for intermittent periods during the day but will be accessible every night.

We appreciate your patience and support while we work to execute these improvements throughout our community! If you have any questions about the Monrovia Renewal Project, please feel free to contact Public Works at (626) 932-5575 or monroviarenewal@ci.monrovia.ca.us.

We recognize that construction can be messy and inconvenient, and we appreciate your patience through this process!


Trees to be Removed and Replaced Related to Monrovia Renewal Work

Throughout the City, a number of trees have been identified as being problematic due to their health and condition as well as the impact they are having on the infrastructure. These trees have been assessed for their overall health and condition and for opportunities to minimize their impact on the infrastructure (such as root pruning or installing root barriers). The ultimate goal is to preserve as many trees as possible; however, in situations when the health of the tree is declining and the trees are impacting the infrastructure, a decision has been made to remove them in coordination with ongoing or upcoming Monrovia Renewal construction activity.
 
As a part of the replacement of the sidewalk, the tree wells will be left intact so that new trees can be planted back in their place. The Field Services team is working to identify suitable replacement trees and will work to replace them when the construction is complete and the planting season is desirable.
 
If you have any questions or concerns, please contact the Public Works Division at (626) 932-5575.


A Note on Construction Schedules...

We are committed to providing you with timely updates on the project's progress and the construction scheduled to take place. Unfortunately, in construction, schedules frequently change at the last minute, due to weather conditions, crew availability, coordination with other agencies, and other unforeseen conditions. We strive to update when these changes occur, and we thank you for your flexibility in advance!


Sewer Cleaning and Closed-Circuit Television (CCTV)

As a part of our routine maintenance program and to facilitate the design of Monrovia Renewal repairs, all of the sewer lines in the City are being cleaned and inspected using Closed Circuit Television (CCTV) technology.

When National Plant Services is out in the field, they use a jetter (or cleaning truck) and a box truck containing the television equipment. The equipment is situated next to sewer manholes located in the road, and the crew takes about 30 minutes at each manhole location. The lines are first cleaned and then inspected utilizing the television equipment.


Supporting Documents


Explore the Improvements Coming to Your Neighborhood!

Monrovia Renewal Phasing Map

To improve efficiency and shorten the construction time spent in each area, Monrovia has been divided into six segments. Construction will occur in each segment according to the timeline below:

  • Southwest and Southeast - 2016 - 2017
  • Northwest and South - 2017 - 2018
  • North - 2018 - 2019
  • Northeast - 2019 - 2020